Most of the projects on this site start with somebody deciding they want a balcony. This one started with somebody who already had one going up, and a growing suspicion that what was being built was not something he wanted to stand on.
He was right. It was the worst piece of balcony work we have ever been called out to. It was being made up on site as it went along, it was already rusting before it was finished, and there was no drawing and no certification behind any of it. The platform, the deck and the part-built balustrade came down, and we built the balcony again from scratch. The nearest thing we sell to the finished job is our walk-out balcony with an infinity frameless glass balustrade.
To be clear about the photographs on this page. The rusting, part-built balcony in the first three pictures is not our work. It is what the customer had been left with, photographed at our survey. Everything we made is further down the page.
Project overview
- Scope: Removal of a part-built balcony by others, then surveyed, drawn, fabricated and installed by us
- Size: Approximately 3.2m wide by 1.2m deep
- Support: Existing concreted posts retained at the customer's request, against our recommendation
- Connection: New frame spigoted into the existing posts, drilled and tapped through
- Frame: Steel, galvanised and then powdercoated to match the existing green windows and doors
- Deck: Composite boards, anthracite grey
- Front balustrade: 17.5mm toughened laminated clear glass in a brushed aluminium base channel
- Side screens: 1800mm high frosted toughened glass privacy screens on stainless steel posts
- Also supplied: Stainless steel and glass balustrade to the patio steps
- Fabrication: BS EN 1090-2, UKCA marked
Been let down on a balcony?
Taking over a part-built job is not something anyone can price from a size. We need to see what is there before we can tell you what can be kept and what has to come out. Send photographs of what you have been left with and you will get a straight answer.
What the customer was left with
The balcony was part built when we were called in. A platform was up, the deck boards were partly laid, and the balustrade had not gone on. These are the things anyone could see standing underneath it:
- Open, unsealed section ends. Hollow steel left with its ends open to the weather, and rust already visible inside them.
- Rust on steelwork that was not even finished yet. Not after a winter in service. Before handover.
- Composite boards cut and left raw. Hollow ends open along the whole edge of the deck, no edge trim, no finishing of any kind.
- Paint brushed on over the top of everything. Run and blobbed around the connections and over cut edges, which is not a coating system, it is decoration.
- Nothing on paper. No drawing, no declaration of performance and no UKCA marking for any of it.
Two ways to build the same balcony
The gap between this job and a proper one is not a matter of degree. They are two completely different ways of working, and the finished article only looks similar from a distance.
How this one was being built. A company turned up with steel and a welder. It was cut and welded together in the garden, on the day, with no drawing to work to and nothing to check it against. Nobody specified a coating, so it was painted on site over bare steel. Nobody set an execution class, because there was no design to set one against. Nobody inspected anything, because there was no quality system to inspect under. And at the end of it the customer had no certification, because there was nothing to certify.
How we build one. We survey the building and measure it. We draw it, and nothing is made until the customer has approved that drawing. It is fabricated in our Sheffield workshop, not in your garden. Where it is worth doing, it is trial built in the workshop so we know it fits before it ever goes on a van. It is hot dip galvanised and then powdercoated, which is a coating system rather than a coat of paint. It arrives as finished components and bolts together on site rather than being welded together in the weather, so the protection stays intact. And it is fabricated under BS EN 1090-2 and UKCA marked, so there is a declaration of performance at the end of it with the customer's name on it.
One of those lasts decades. The other was rusting before it was finished.
Why it came down rather than being patched up
The obvious question is why we did not just finish it off. Cap the open ends, trim the deck, fit a balustrade on top and move on. It would have been quicker and it would have been cheaper for the customer.
Because it would have meant putting our name on somebody else's structure.
A balcony is a barrier at height with people standing on it. Ours are fabricated under BS EN 1090-2, which means a drawing, a specified execution class, a known welding procedure and a declaration at the end. None of that existed here, so there was nothing to inspect it against and nothing to certify. That is not something you create retrospectively by tidying up the bits you can see.
And rust on steelwork that has not even been handed over tells you the protection was wrong from the first day. You do not fix that with another coat of paint over the top of it.
So it came down.
The posts stayed, and that was the customer's decision
The posts were already concreted in, and a new patio had been laid up to them. Taking them out meant lifting new paving as well as taking the balcony down, and this was a customer who had already paid once for a balcony he could not use.
Our recommendation was to replace them. They appeared solid at survey, but they were not ours, we had no record of what was underneath them, and they came from the same job as everything else we had just condemned.
The customer chose to keep them, and on a tight budget we understood why. What matters is what happened next, because this is the part that protects everybody. We made it clear that we could not warrant the existing posts in any way, and the decision to retain them was recorded on the drawing the customer approved before anything was made.
That is how a specification chosen against our advice should be dealt with. We tell you what we would do, you decide, and the decision goes on the drawing with your approval against it. What we will not do is quietly take somebody else's structure into our guarantee and say nothing.
The new frame connects into the posts on internal spigots, drilled and tapped through, so the platform is located and fixed inside the existing uprights rather than clamped onto the outside of them.
What went back up
A rectangular hollow section frame with angle joists across it, hot dip galvanised and then powdercoated to match the green of the windows, doors and existing posts. Composite decking in anthracite grey.
The front balustrade is 17.5mm toughened laminated clear glass held in a brushed finish aluminium base channel, with no posts across the front, so nothing interrupts the view out of the doors. The two sides are deliberately different: 1800mm high frosted toughened glass privacy screens on stainless steel posts, so the balcony is usable without overlooking the neighbours or being overlooked.
All of it drawn, fabricated and finished in our workshop before it came to site, and all of it UKCA marked. This customer now has the drawing and the declaration of performance he never got the first time.
While we were on site we also fitted a stainless steel and glass balustrade to the patio steps below, which is our System 1.
The part nobody budgets for
This customer paid for a balcony twice.
He paid somebody to build one, and then he paid us to take that away and build it again. The second bill included removing and disposing of work he had already bought and could never use.
That is the real cost of the cheapest quote, and it is never the number you are comparing when you are choosing. You think you are saving money. Then the cowboys stop answering the phone, you are left with a job you cannot use and cannot certify, and you have to put it right anyway. It ends up costing more than doing it properly in the first place.
We are not the cheapest and we have never pretended to be. What we are is a company that is still here, with a drawing, a declaration of performance and a UKCA mark at the end of the job.
What to ask before you place an order
None of this is difficult to check and it takes one email. Ask whoever is quoting you:
- Will it be UKCA marked, and will I get a declaration of performance? Structural steelwork for a balcony or a balustrade should be. If the answer is vague, that is your answer.
- Who certifies you, and what is your certificate number? Ours is BS EN 1090 through ISOQAR, UKAS 0026, UKCA 0513. A real one can be quoted without hesitation.
- What execution class is it being fabricated to? If nobody has set one, there is no design behind the job.
- Where will it actually be made? A balcony should arrive as finished components and bolt together. If it is going to be cut and welded in your garden, you are buying what this customer bought.
- Will I see and approve a drawing before anything is made? If there is no drawing, there is nothing to hold anyone to later.
- What is the coating system? Galvanised and then powdercoated is a system. Painted on site is not.
- What is guaranteed, what is excluded, and for how long? Get the exclusions in writing, not just the guarantee.
And check the company, not just the quote
We always encourage people to do their own due diligence before they place an order with anybody, including us. It costs nothing and it is the single best protection there is.
- Read the reviews, and read the bad ones as well as the good ones.
- Check how long they have been trading. Companies House is free. A balcony is supposed to outlast the company that fitted it.
- Look at the website properly. Is there real work on it, photographed on real houses, or is it stock images and no projects?
- Ask for testimonials, and ask whether you can speak to a past customer.
- Ask to visit. A fabricator with a workshop will let you come and see it. If there is no address, ask yourself where the work is being made.
- Check the certification rather than taking the logo on the website at face value.
Our own answers are on the UKCA certification page, the about us page and our testimonials, we have been making metalwork in Sheffield for over 35 years, and you are welcome to come and see work being made in the workshop.
Get a price for something similar
Send photographs of the elevation and a rough size to sales@diomet.co.uk, or call 0114 243 9009. If you are taking over a part-built job, send photographs of what is already there as well, including anything underground if you have it, and say what you have been given on paper.
- Infinity frameless walk-out balcony, the closest product to the one that went back up, with no posts across the front
- Walk-out balcony with a framed glass balustrade, the posted version, which costs less
- Walk-out balcony with a walk-on glass floor, where the daylight below matters
- System 1 stainless steel and glass balustrade, as fitted to the steps on this job
- Glass spigot balustrade and privacy screens, for frosted screening on an existing deck or patio
If you are not sure what to send, our how to get a price page sets it out.
Before you order
- UKCA certified balustrades, balconies and staircases
- Balcony building regulations
- BS 6180 barrier and balustrade loadings
- Retrofitting a balcony to an existing house
- Walk-out balcony FAQ
- Trial building in our Sheffield workshop
- Material finishes
- Delivery and installation
Frequently asked questions
Can you take over a balcony somebody else has started?
Yes, and we are asked fairly often. What we cannot do is certify work we did not make, so the honest answer usually involves removing some of it. We will tell you at survey what can stay and what cannot, and why.
How do I know whether a balcony is properly certified?
Ask for the UKCA marking and the declaration of performance, and ask which body certifies the fabricator and under what number. Structural steelwork for a balcony falls under BS EN 1090. A company that works to it will answer in one line. A company that does not will change the subject.
Is a balcony welded together on site a problem in itself?
It is a very strong warning sign. Site welding on a domestic balcony means there is no drawing being worked to, no controlled welding procedure and no coating system, because you cannot galvanise something after you have welded it together in a garden. Properly made balconies are fabricated and finished in a workshop and bolted together on site.
Can existing posts or footings be reused?
Sometimes, but it is the customer's decision and it comes with a condition. We will survey what is there and tell you what we would do. If you choose to keep something we did not install, we will say plainly that it falls outside what we can warrant, and that will be recorded on the drawing you approve.
Why would a new balcony already be rusting?
Because it was painted rather than coated. Bare steel cut and welded on site, brushed over with paint and left with open section ends will start to rust from the inside and from every cut edge. Galvanising goes on before the finish coat and protects the steel even where the surface gets damaged.
Is the cheapest quote always the wrong one?
No, and we are not going to pretend otherwise. But if one quote is dramatically below the others, find out what is missing from it rather than assuming you have found a bargain. It is usually the drawing, the certification, the coating system or all three.
Other projects like this one
- Replacing a failed timber balcony with steel and composite decking, Nuneaton
- Two storey walk-out balcony with stairs, Sheffield
- Walk-out balcony with privacy screening, Surrey
- UKCA certified fire escape staircase, London E17
- Glass balustrade replacement on a school staircase, York
- View all our bespoke projects